Arizona Plumbing Contractor (C-37/CR-37) Trade Exam Exam Prep
Free practice questions

Free AZ-PLB Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The AZ-PLB exam has 100 questions and runs 4 hours.

These 10 free AZ-PLB questions are organized by exam domain, so you can see how each part of the Arizona Plumbing Contractor (C-37/CR-37) Trade Exam blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Drainage Waste and Vents

Question 1

Four connections are visible during a drainage rough-in inspection. Which installation needs to be changed under the 2018 International Plumbing Code?

Show answer & explanation

Correct answer: C - A vertical soil stack enters a horizontal building drain through a sanitary tee laid on its back.

Question 2

Cabinet offsets make a 2-inch sink trap arm 9 feet long along the pipe centerline, although the trap and dry-vent connection are only 6 feet apart in a straight line. The entire trap arm slopes 1/4 inch per foot. Which proposal corrects the trap-to-vent distance under the 2018 IPC?

Show answer & explanation

Correct answer: A - Move the vent takeoff so the developed trap-arm length is 7 feet.

Domain 3: Water Supply Systems

Question 3

Weak flow is reported throughout a building. Gauges immediately before and after a cartridge filter both read 64 psi with all fixtures closed. During simultaneous fixture use, the upstream gauge reads 60 psi and the downstream gauge reads 27 psi. No valve or regulator is located between the two gauge taps. Where should troubleshooting begin?

Show answer & explanation

Correct answer: A - Inspect the filter element and housing for a restriction.

Domain 4: Backflow Prevention

Question 4

A chemical-treatment line containing a solution classified as a health hazard receives potable make-up water. A downstream pump can raise the solution's pressure above the water-supply pressure. The design requires a continuously pressurized, directly piped connection rather than a break tank. Which protection matches both the hazard and the possible backpressure?

Show answer & explanation

Correct answer: B - A reduced-pressure-principle backflow prevention assembly

Domain 5: Roof Drains and Storm Drainage Systems

Question 5

A parapet-enclosed roof has separate primary and secondary drain inlets, but their pipes join one horizontal collector inside the building. The collector has sufficient capacity for both calculated flows. What change is still necessary to meet the 2018 IPC secondary-drainage requirements?

Show answer & explanation

Correct answer: D - Route the secondary drain independently to an observable discharge.

Domain 6: Plumbing Fixtures (including water heaters and accessibility)

Question 6

An adult public restroom has a wheelchair-accessible compartment with a floor-mounted water closet. Clear inside dimensions are 62 inches wide by 57 inches deep. The toilet centerline is 17 inches from the side partition, and the top of the seat is 18 inches above the finished floor. The door swings outward, and required toe clearances are provided. Which measured dimension needs revision under the 2010 ADA Standards?

Show answer & explanation

Correct answer: B - The 57-inch clear compartment depth

Domain 7: General Knowledge

Question 7

Two 45-degree copper elbows will shift a water line to a parallel run whose centerline is 18 inches away, measured perpendicular to the runs. Each elbow has a 1.25-inch takeout measured from the centerline intersection to the internal tube stop. Approximately how long should the straight tube between the elbows be cut?

Show answer & explanation

Correct answer: C - 23.0 inches

Domain 9: Fuel Gas

Question 8

A natural-gas system serves a furnace rated at 100,000 Btu/h input and 80,000 Btu/h output, plus a water heater rated at 40,000 Btu/h input. From the point of delivery, developed lengths are 74 feet to the furnace and 38 feet to the water heater. The common supply segment is 25 feet long. The applicable sizing table includes 30-, 40-, 60-, and 80-foot rows, and the gas heating value is 1,000 Btu per cubic foot. Using the 2018 IFGC longest-length method, which row and demand apply to the common segment?

Show answer & explanation

Correct answer: D - 80-foot row; 140 cubic feet per hour

Domain 10: Septic and Sewer

Question 9

On an Arizona conventional septic installation, a crew proposes carrying the building sewer's 1/8-inch-per-foot slope into the perforated disposal piping in the aggregate-filled absorption trenches. The correct instruction under A.A.C. R18-9-E302 is to:

Show answer & explanation

Correct answer: D - Install both the trench bottoms and the disposal pipes level.

Domain 13: Excavation

Question 10

Before work begins in a trench 4 feet 6 inches deep, a competent person examines the ground and finds no indication of a potential cave-in. Spoil is retained 3 feet from the edge, and no other hazards are identified. The only ladder is 32 feet laterally from the planned work position. Which change is required by OSHA for that work position?

Show answer & explanation

Correct answer: A - Position another secured ladder 15 feet from the work area.

The rest of the AZ-PLB blueprint

The AZ-PLB exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more AZ-PLB questions with explanations.

Continue in the free practice test →